Network Rail
Black Diamond

Nichols were engaged to lead the Black Diamond Review, a strategic review of the west coast route modernisation restructuring programme. A new strategy was developed to satisfy the programme commitments and improve confidence in successful implementation.

Challenge
Railtrack’s original strategy for West Coast Route Modernisation (WCRM) was the basis for contractual commitments with Virgin and Undertakings to the Rail Regulator in 1998. Following a review and restructuring of WCRM, concerns were raised about the ability of the programme to meet the Phase 2 outputs by May 2005. Of particular concern was the new, moving-block signalling system. Railtrack engaged Nichols to lead an immediate review of the Phase 2 implementation strategy.

Nichols_Group_Network_Rail_Black_Diamond_Slider3

Experience
We formed a strong, lean, integrated team including specialists from Nichols, Railtrack, control systems contractors and other consultants.

Drawing upon our Lean and Assured Management of Projects and Programmes principles, we challenged the delivery strategy, the scope of deliverables and all existing assumptions. We commissioned international research into the availability and status of control system options around the world and those available were assessed for suitability. Combinations of infrastructure schemes and alternative control systems were then considered in a series of scenarios. Timetabled services were re-modelled to simulate the effects of the proposed changes to infrastructure and control systems. We considered changing the baseline to resolve the outstanding timetable issues and assessed them using expert analysis and modelling.

Strategic review of West Coast Route Modernisation Programme

Benefits
As a result of our work, a new strategy was developed for Phase 2 that could satisfy both commitments to Virgin and the majority of the Undertakings to the Rail Regulator within the May 2005 timeframe.

The revised strategy improved confidence that Phase 2 could be successfully implemented within the timescales quoted. It was endorsed at a Railtrack Board meeting in December 1999. The Black Diamond Review was subsequently adopted as basis of delivery strategy for West Coast Route Modernisation.

Stories

London 2012 Olympic
and Paralympic Games
Nichols_Group_London_2012_Olympics_Thumbnail
Transport for London Nichols-TFL Crossrail Nichols_Group_Crossrail_Thumbnail Nuclear Decommissioning Authority Nichols_Group_Nuclear_Decommissioning_Authority_Thumbnail Thales Nichols-Thales-Thumbnail Anglo American Nichols-Anglo-American Department for Transport Nichols_Group_Department_For_Transport_Thumbnail Sellafield Nichols_Group_Sellafield_Thumbnail Office of Rail Regulation Nichols_Group_Office_For_Rail_Regulation_Thumbnail

Iconic Stories

Jubilee Line Extension Nichols-Jubilee-Line Highways Agency Nichols-Highways-Agency Docklands Light Railway Nichols-DLR Hong Kong West
Kowloon Expressway
Nichols-Hong-Kong-West-Kowloon-Expressway-Thumbnail
AVIVA Nichols-AVIVA Crossrail Early Years Nichols_Group_Crossrail_Early_Years_Thumbnail Department for Transport Intercity Express Programme Nichols_Group_Department_for_Transport_Intercity_Express_Programme_Thumbnail Transport for London
Capital Programmes
Delivery Capability
Nichols-Transport-For-London-Capability-Programmes
Hong Kong
Highways Department
Nichols-Kong-Kong-Highways-Department
Network Rail Black Diamond Nichols-Network-Rail-Black-Diamond-thumb A Major UK Bank Nichols-A-Major-UK-Bank Network Rail
Improving Delivery
Nichols_Group_Network_Rail_Improving_Delivery_Thumbnail